THE MOST IMPORTANT WORKS IN 2001-2003
Name | Modernization of AR-2c Datalogger used in hoist in # I eastern - signals registration from safe circuit, additional analog and binary signals registration. |
Executed works scope |
- Supply and installation of TSSA Emergency Brake Logger
- AR-2c Datalogger modernization - additional binary and analog inputs extension
- Reprogramming, testing and startup of AR-2c in new configuration
|
Time range | August 2001 |
Investor/General Contractor | PMUE S.A. |
Installation special features | cooperation with TSSA system |
Name | Elaboration, realization and installation of Digital Shaft Set WJG-1 for portable hoist used for shaft revision |
Executed works scope |
- Analysis of law requirements and development of functional guidelines and technical realization
- Development of technical project and DTR
- Device build, installation and testing as in documentation
- Parametrization and startup
|
Time range | January 2002 |
Investor/General Contractor | Centrum Elektryfikacji i Automatyzacji Górnictwa ''EMAG'' |
Installation special features | Specimen specialized to work in heavy environment - on portable hoist for shaft revision. WJG-1 software and hardware adaptation to cooperation with video recorder (video signal pass on) |
Name | Supervision system elaboration for temperature measurement and control system on current carrying busbar connections that source machines, with specialized visualization software |
Executed works scope |
- Functional guidelines development
- Switchboard (data concentrator) model build
- Installation and testing in industrial hall
- Client software for process visualization elaboration
- MicroLAN and MODBUS RTU networks integration
|
Time range | May 2001 - September 2002 |
Investor/General Contractor | Monitoring Systems & Control, LLC from Florida USA |
Installation special features | complete supervision and monitoring system based on 1-Wire and MODBUS RTU (mixed topology) industrial network technology that can work on big industrial area, slow variable physical processes supervision and observation, designed for power supply networks predictive supervision |
Gallery
Name | Server elaboration and programing to implement AR-2c Dataloggers access through TCP/IP - archetype application on Staszic Coal Mine |
Executed works scope |
- Server software development with ''ar2c_lp'' native protocol frames tunneling in standard TCP/IP frames
- Logger 2.0 visualization and communication application upgrade to network version Logger 3.0 that uses server program
- Net version of Logger development for all AR-2c Dataloggers installed in Staszic coal mine
- Build, testing and validation of network access to AR-2c Dataloggers, in Staszic coal mine, archetype application
|
Time range | July 2003 |
Investor/General Contractor | Z.E.U.S. MicroSTER in cooperation with KWK Staszic |
Installation special features | Promotional installation as a training ground |
Name | AR-2c Datalogger modernization at # VI KWK Budryk to adaptation it to receive signals from USS through PROFIBUS DP bus |
Executed works scope |
- Build and installing prototype PROFIBUS DP communication card in AR-2c that enables signal receiving form USS build on PLC's
- 8 analog inputs (POMMAX type) card supply
- Measurement of main and induction current
- Measurement of operational and emergency braking system pressure
- AR-2c application development to enclose in registration signals received through PROFIBUS DP bus
- New Logger application version elaborate that enables new signals visualization
|
Time range | December 2003 |
Investor/General Contractor | P.P.U.H Elcam Sp. z o.o. |
Installation special features | First AR type logger that supports signal collection form PLC-based devices, through industrial communication protocols |
Gallery