THE MOST IMPORTANT WORKS IN 2012

NameModernization of AR-2c Datalogger to AR-3c version in hoist #Grunwald IV KWK Halemba
Executed works scope
  • Modernization of AR-2c Datalogger to AR-3c version
  • Startup of Ethernet IP module
Time rangeApril 2012
Investor/General ContractorP.P.H.U. Elcam Sp. z o.o.
Installation special features---
NameSupply of AR-3c Datalogger for Skipowaja mine in P.P.H.U. Elcam Sp z o.o.'s order
Executed works scope
  • Supply of AR-4c Datalogger
Time rangeApril 2012
Investor/General ContractorP.P.H.U. Elcam Sp. z o.o.
Installation special features---
NameModernization of Datalogger to AR-2c version in hoist #R IV Olko and #R IV emergency-revisory shaft ZG Rudna
Executed works scope
  • Modernization of Datalogger to AR-2c+ version
Time rangeMay 2012
Investor/General ContractorKGHM Polska Miedź A.S. ZG Rudna
Installation special features---
NameStartup of AR-3c Datalogger in hoist #IV KWK Piast
Executed works scope
  • Startup of AR-3c Datalogger
  • Visualization startup
Time rangeMay 2012
Investor/General ContractorKompania Węglowa S.A. o/KWK Piast
Installation special features---
NameSupply and startup of Ar-4c Datalogger in hoist #R IX ZG Rudna
Executed works scope
  • Supply and startup of AR-4c Datalogger
Time rangeJuly 2012
Investor/General ContractorDagtech Sp. z o.o.
Installation special features---
NameModernization of AR-2c Datalogger to AR-3c version on Podsadzkowy shaft KWK Marcel
Executed works scope
  • Modernization AR-2c Datalogger to AR-3c version
Time rangeJuly 2012
Investor/General ContractorKompania Węglowa S.A. o/KWK Marcel
Installation special features---
NameSupply of AR-3c Dataloggers (2 pcs) in hoist #CSA2 in Karvina
Executed works scope
  • Supply of two pieces of AR-3c Dataloggers
  • Supply of two encoders for speed measurement
  • Supply of two pieces of visualization system
Time rangeAugust 2012
Investor/General ContractorP.P.H.U. Elcam Sp. z o.o.
Installation special features---
NameSupply of AR-4c Dataloggers (3 pcs) for installation in Russian Federacy
Executed works scope
  • Supply of AR-4c Dataloggers (3 pcs)
Time rangeAugust 2012
Investor/General ContractorMidiel Ltd.
Installation special features---
NameSupply of AR-4c Dataloggers (2 pcs) in hoist #Wołgokalij in Eurochin mine
Executed works scope
  • Supply of two AR-4c Dataloggers with Ethernet IP communication modules and encoders for speed measurement
Time rangeNovember 2012
Investor/General ContractorP.P.H.U. Elcam Sp. z o.o.
Installation special features---
NameInstallation of current and pressure measurement
Executed works scope
  • in hoist #III Z, #IV KWK Bielszowice - January 2012
  • in hoist #Wanda I, # Wanda II KWK Pokój - January 2012
  • in hoist #Lech II KWK Pokój - March 2012
  • in hoist #Lech I KWK Pokój - April 2012
  • in hoist #I north-east and #I south-west KWK Zofiówka - May 2012
  • in hoist #III W and #III Z KWK Marcel - November 2012
  • in hoist #III, #II Z and #II W KWK Krupiński - November 2012
  • in hoist #Wiktor KWK Marcel - December 2012
Time rangeYear 2012
Investor/General Contractor---
Installation special features---
NameSupply of visualization systems
Executed works scope
  • Supply of visualization for Karvina mine on PBSz S.A.'s order - August 2012
  • Supply of visualization in hoist IV KWK Knurów – Szczygłowice - September 2012
Time rangeYear 2012
Investor/General Contractor---
Installation special features---
NameProxy servers' installations
Executed works scope
  • KWK Centrum - February 2012
  • KWK Halemba - April 2012
  • KWK Knurów – Szczygłowice ruch Szczygłowice - July 2012
  • KWK Pokój - July 2012
  • KWK Jas-MOS - September 2012
  • KWK Jankowice - December 2012
  • KWK Krupiński - December 2012
Time rangeYear 2012
Investor/General Contractor---
Installation special features---